EVMS Guideline 02 - Delivery Organization
Guideline
Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work, and define the organizational elements in which work will be planned and controlled.
Interpretation
Identify organizational structure (OBS) for planning, controlling, and accomplishing the work.